Planning approval for Stadium expansion to be sought despite setback

Published:

Despite the recent announcement that the Federal Government will not contribute $20 million in the upcoming Federal budget towards the $68 million Sunshine Coast Stadium expansion, Sunshine Coast Council is continuing work so the project is shovel ready should that funding become available in the future.

An important part of that work is obtaining the planning approval for the Stadium Expansion project.

In January 2021, council submitted the development application to the Queensland Government via the Ministerial Infrastructure Designation (MID) process and the government today (February 16) started the required 20-business day community consultation period.

The MID application process means council does not assess its own development application.

The MID process is commonly used for community infrastructure such as schools, hospitals and sporting clubs.

“While the project cannot now proceed on its original timeline, submitting the development application to the Queensland Government was an important step towards having the project ready to proceed in the future, if and when Federal Government funding is secured,” Sunshine Coast Council Mayor Mark Jamieson said.

Whilst we are obviously disappointed by the Federal Government’s decision, we will continue to work with their representatives to convince them of the need for this project, the strong local support it enjoys and to secure the required $20 million.

“Ultimately, an expanded Sunshine Coast Stadium will help to address a missing piece of economic and community infrastructure for a region of our size and its projected growth.

“As a stimulus project, the Sunshine Coast Stadium expansion ticks all the boxes. More than 300 jobs would be created during construction and over $25 million in ongoing annual economic benefits for the region.”

Project details:

The MID application proposes an expansion of the Sunshine Coast Stadium to a venue seating capacity to 11,618 with a total capacity of 16,618 via:

  • construction of a new eastern grandstand that will seat just over 8000 spectators and include food and beverage outlets and amenities;
  • expansion of the existing western grandstand to seat 3533 spectators and add improved facilities for athletes and officials, multi-purpose community spaces, improved first aid facilities, improved amenities and an enhanced hospitality and function offering;
  • southern and northern mounds will remain to accommodate around 5000 spectators.

Consultation

If you would like to view the stadium expansion plans and make a submission, visit the Queensland Government website  https://planning.dsdmip.qld.gov.au/id-consultations  

Submissions close March 17, 2021.

Submissions can be made via the website, email to infrastructuredesignation@dsdmip.qld.gov.au or post to GPO Box 611, Brisbane, QLD, 4001.

To discuss the proposal, please contact the Infrastructure Designations team within the Queensland Government Department of State Development, Infrastructure, Local Government and Planning on 1300 967 433 or at the above email address.

For more information about the expansion project visit council’s website https://www.sunshinecoast.qld.gov.au/Council/Planning-and-Projects/Major-Regional-Projects/Sunshine-Coast-Stadium-Expansion

 
Australian Government Business Business & Economy Entertainment Infrastructure & Construction Lifestyle Queensland Government Sunshine Coast Council
Social:   

Sunshine Coast Regional Council :
Locked Bag 72 Sunshine Coast Mail Centre Q 4560, Sunshine Coast Wide
07 5475 7272
1300 007 272
Sunshine Coast Regional Council
Showing 10+ recent articles for this business
Ten-year heritage plan gets the green light 25 February 2021 | Sunshine Coast Council today (25 February) endorsed a 10-year heritage plan to protect and engage our residents and visitors in the region’s cultural heritage. More information...
Planning approval for Stadium expansion to be sought despite setback 16 February 2021 | Despite the recent announcement that the Federal Government will not contribute $20 million in the upcoming Federal budget towards the $68 million Sunshine Coast Stadium expansion, Sunshine Coast Council is... More information...
Nominate a young conservationist now 02 February 2021 | If you know a young eco-warrior, now is the time to nominate them for the Les Hall Young Conservationist Award and recognise their efforts. More information...
Improve your Sunshine Coast journey with Roads Hub 03 February 2021 | Did you know Sunshine Coast Council offers a free online tool to help residents and visitors better navigate local roads? More information...
Council support is music to the ears of Maleny singer 08 February 2021 | Maleny local Natalie Gauci is among 11 Sunshine Coast region creative arts workers to share in more than $65,000 in Regional Arts Development Funding (RADF). More information...
Council's Major Grants program now open – apply today! 01 February 2021 | Does your community group have a great project idea to make our local communities more active, vibrant, inclusive, resilient or creative? Make it a reality with support from Sunshine Coast Council's Community... More information...
Community safety update: Buderim Forest Park pedestrian bridge temporarily closed 29 January 2021 | Important maintenance works are underway on Serenity Bridge in Buderim Forest Park, limiting access to some walking trails. More information...
Sunshine Coast's first high support needs amenities open 27 January 2021 | One of the Sunshine Coast's premier parks is now home to the region's first Changing Places public amenities block, catering for people with high support needs who can't use accessible toilets. More information...
Where are you and where did you come from 22 January 2021 | Peeking into your family’s past, unearthing fortunes lost and found, tucked away tragedies and surprise secrets—it’s a personal voyeurism like no other but how do you do it and where do you start? More information...
Free green waste disposal extended as post storm clean-up continues 18 January 2021 | Extensive recovery works by Sunshine Coast Council are still underway in response to Saturday’s powerful storm cell which most impacted the region’s southern suburbs. More information...


comments powered by Disqus

All articles submitted by third parties or written by My Sunshine Coast come under our Disclaimer / Terms of Service